Another 1000 RKM Electrification work will be ready by end of September 2019.
Government of India is committed to provide fast,efficient and safe Rail transportation through Railway Electrification.
Central Organisation for Railway Electrification
6,704 posts
Official Twitter handle of CORE.Dedicated to provide Efficient, Fast and Environment friendly Rail Transportation through Railway Electrification.
- First Goods Train run on Electric Traction from Ahmedabad to Viram gram Successfully completed. Approx saving of ₹ 22,200/- in one trip,450 litre of diesel saved and 1600 units of electricity spent. @RailMinIndia @WesternRly @drmadiwr
- CRS inspection of Bhatiya- Dwarka-Okha section (70 RKM) of Rajkot Division in Western Railway completed successfully on 09.02.2022.
- Railway Electrification work of katni -satna 95 RKM in the territory of WCR completed on 29.06.2020. Total electrification completed by CORE in 2020-21 stands 181 RKM. Journey from Mumbai to Howrah/Patna will now be without traction change in between.
- First Electric Double stack containerTrain ran successfully fromPalanpur toBotad via MSH(Gr187) VG (Gr213)SUNR (Gr212)and reachedBotad today at around11.45Hrs after covering270RKM.This is the first loaded double stack container train onElectricTraction with High Rise pantographs.
00:00 - CRS inspection of Salem-Vriddhachalam section (136 RKM) of Salem Division in Southern Railway completed successfully on 28.12.2021. With this total 1192.81 RKM route have been electrified by CORE in the current FY.
- OHE energisation, earth fault test followed by AC loco trial in Birur Arsikere section of Mysuru Division of South Western Railway (42 RKM) completed successfully in UP & DN both directions on 28.11.22. @RailMinIndia @SWRRLY #missionelectrification
- OHE energisation, earth fault test followed by Light engine trial of Gadag bypass line of Hubli Division SWR (1.84 RKM, 3.54 TKM) completed successfully in UP & DN both directions. @SWRRLY
- Inspection of Railway Electrification works followed by speed trial at full sectional speed in Hosdurga (Excl)- Birur (Incl) Section (38.7 RKM /91.72 TKM Double line), MYS Division of South Western Railway completed successfully today. @SWRRLY
- CRS inspection of Barabanki-Ayodhya Cantt. (99.25 RKM) Lucknow Division in Northen Railway completed successfully on 30.03.2022. With this total 4220.26 RKM route have been electrified by CORE in the current FY.@RailMinIndia @GM_NRly
- CRS inspection of Gadwal-Raichur section (57.7 RKM) of Hyderabd Decan Nampally & Guntakal Division in South Cetral Railway completed successfully on 21.12.2021. With this total 1032.81 RKM route have been electrified by CORE in the current FY.
- CRS inspection of New Jalpaiguri- Raninagar Jalpaiguri section (28 rkm/ 66 tkm) of Katihar division including speed trial completed successfully today.
- CRS inspection of Dhalgaon - Kurduwadi section (125 RKM) of Solapur Division in Central Railway completed successfully on 04.03.2021. With this total 1337 RKM route have been electrified by CORE in the current FY.
- CORE is striving hard to electrify existing railway lines.Light Engine trial of Madalgarh -Jalandhari section completed on 19.12.20.