Hi Elizabeth,
Thanks for getting in touch and sorry for the delay from my side.
I am glad to hear you were able to find it. Thanks for the feedback, I will definitely re-label it in the next version.
Thanks again.
Kindest regards,
Dylan
Hopefully last question, do you have an example spreadsheet that shows importing with child tasks? The example shows only parents and exporting tasks from my installation shows only parent tasks inspite of exporting at both the parent an subtask levels.
Thank you.
Future addition: move tasks to either promote to main task or from one parent to another.
All the best,
Elizabeth
Hi Elizabeth,
Thanks for the question, and please feel free to ask as many questions as needed, I am happy to help.
Regarding importing child tasks, this can be done by setting the “Parent ID” column in the CSV to the ID of the parent it should be a child of. I found the cause of the subtasks not exporting correctly when exporting via the plugin dashboard, and this is resolved now in the updated version here (this will be moved live this week if you would like to wait for the official release, but if it is urgent, the version below can be installed to replace the current Basic version):
https://drive.google.com/file/d/1JkyKYRbMdYLQBxoIjTBg6edL2M1yeSex/view?usp=sharing
Thanks for the suggestion of promoting to main task – I have added this to the request list to add in the future.
I hope this helps.
Kindest regards,
Dylan