Skip to content

Fix MSLF IPH Installed cost per capacity calculation error #1082

Merged
taylorbrown75 merged 2 commits into
developfrom
MSLF_capital_cost_bug
Nov 17, 2023
Merged

Fix MSLF IPH Installed cost per capacity calculation error #1082
taylorbrown75 merged 2 commits into
developfrom
MSLF_capital_cost_bug

Conversation

@taylorbrown75

Copy link
Copy Markdown
Collaborator

Fix issue #1081 https://github.com/NREL/ssc/issues/1081

Fix Installed cost per capacity calculation caused by unit conversion error.

@taylorbrown75 taylorbrown75 added the csp concentrating solar power label Oct 30, 2023
@taylorbrown75 taylorbrown75 added this to the SAM Fall 2023 Release milestone Oct 30, 2023
@taylorbrown75 taylorbrown75 self-assigned this Oct 30, 2023
@taylorbrown75 taylorbrown75 linked an issue Oct 30, 2023 that may be closed by this pull request
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Labels

added to release notes csp concentrating solar power

Projects

None yet

Development

Successfully merging this pull request may close these issues.

MSLF IPH Installed cost per capacity calculation error