Update land use calculations for consistency and industry rules of thumb #1143

@brtietz

Description

@brtietz

Describe the bug

The papers and podcast episode below suggest that average land use per MW should be more like 5 - 10 acres/MW, where as detailed PV suggests 3 acres/MW, and PVWatts suggests 9.4

https://www.nrel.gov/docs/fy13osti/56290.pdf
https://xenetwork.org/ets/episodes/episode-175-community-support-and-opposition/
https://emp.lbl.gov/publications/land-requirements-utility-scale-pv

To Reproduce

Steps to reproduce the behavior:

  1. Open default cases as described above
  2. Change DC system size to 1 MW
  3. See error

Expected behavior

Land use calculations should lead to results consistent with the above resources, and be consistent between models

Total Module Area

Consider using same convention for PVWatts and Detailed PV: PVWatts "Estimated total module area" and Detailed PV "Total module area" shown on System Design page should be total of all module areas rather than total module area projected onto ground, i.e., not be affected by GCR. GCR should only affect land area in acres/ha on PV Land Area form.

  • Verify that this approach is consistent with all uses of GCR: Self shading, backtracking, and land area for both Detailed PV and PVWatts models.

  • Note module area on Detailed PV Module and Shading and Layout page: Total module area on system design page should be area of single module times total number of modules.

Metadata

Metadata

Labels

Type

No type
No fields configured for issues without a type.

Projects

No projects

Relationships

None yet

Development

No branches or pull requests

Issue actions