CT Replacement

Outdoor power station Rev Power Solutions

Kettles Hill Wind Farm

CT Replacement

Kettles Hill is a wind farm located along the Foothills of Pincher Creek. As a farm set up for growth, REV was thrilled to have been awarded a project with the wind farm to replace its CT’s.

The Kettles Hill CT’s were found cracked during maintenance, where they were being tested to ensure that they would last another year. When the CT’s were found this way, the farm was shut down and the decision was made that all 26 CT’s were to be replaced. They were replaced with donut CT’s weighing up to 100lbs each, and were installed at a low temperature in order to avoid future cracking. After installation, the new CT’s were tested and recommissioned to the protective relays and meters.

  • Gallery Image
  • Gallery Image
  • Gallery Image

    Project Details

    YEAR 2015

    Discovery 36 CT’s were tested to ensure they would continue to work over the next year, but were found cracked.

    Description All 36 CT’s were replaced and tested after installation and have been up and running without interruption ever since.

    Contact Us

    Responsibly and Reliably Powering Industry

    We want to hear from you! Whether it is an inquiry or question, customer feedback, or just a quick hello, we are always interested in what YOU have to say.
    Let's Get Started

    Share this Project: