Geothermal Drilling cost curve updates#910
Conversation
* Clean up battery dispatch UI forms Click through battery dispatch forms for PV Battery, Generic Battery, Standalone Battery, and Fuel Cell and try all options to fix any problems with callbacks or messages for FOM (Single Owner) and BTM (Commercial) * Change dispatch group labels to match radio button choices * Fix dispatch choice callback error for non-fuel cell techs * Clean up custom weather file inputs * Fix variable group names and labels for variable browsers * Fix labels for BTM peak shaving load growth * Fix UI checks on fuel cell and battery manual dispatch Also, disable "charge battery from fuel cell" check boxes when battery is disabled.
* remove tax incentive and switch financing debt mode * update etes default capacity payment, ppa price, and debt terms * update test results for new ETES defaults
* update physical trough ppa defaults * update mspt and empirical trough ppa defaults * update msLF trough ppa defaults * update DSLF trough ppa defaults * update Generic CSP ppa defaults * switch flip years to 9 * update test results for updated csp financial defaults
injection drilling cost plot
|
@cpaulgilman I could use some interface design notes on this |
|
@mjprilliman This is pretty cool. Nice work! I can make couple of small tweaks to make the layout clearer if you don't mind. A couple of questions:
|
|
Description
-Update drilling and injection cost curves to be based off scenario (4 options), well diameter (2 options), and well type (2 options)
-Add plot showing where along the cost curve scenarios the selection lies
-interface redesign